625 and 650 Electrical Line Upgrade Project
6 Documents in Project
Summary
SCH Number
2012032066
Lead Agency
Tahoe Regional Planning Agency
(TRPA)
Document Title
625 and 650 Electrical Line Upgrade Project
Document Type
NOD - Notice of Determination
Received
Posted
4/13/2015
Present Land Use
As specified in : Kings Beach, Tahoe City, Community Plan; Truckee, Placer Cournt General Plans; Mrtis Valley Community Plan
Document Description
The project would upgrade of CalPeco's existing 625 and 650 electrical power lines and associated substations from 60 kilovolt (kV) to 120 kV to allow the entire North Lake Tahoe Transmission System to operate at 120 kV. The project would include: 1) removal of the existing 625 Line and construction of a new, rerouted 625 Line; 2) rebuild of the existing 650 Line; 3) partial realignment of the 650 Line; 4) rebuild of the Northstar Tap into a fold; 5) rebuild of a section of the existing 132 Line in the Town of Truckee; and 6) upgrade, modification, and/or decommissioning of six substations. These improvements would increase the ability to maintain the current maximum system loads.
Contact Information
Name
Michael Rosauer
Agency Name
CA Public Utilities Commission
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Cities
Nevada City, Truckee
Counties
Placer
Cross Streets
SR 89/SR 28; SR 267/SR 28; BrockwayRoad/Donner Pass Road
Zip
96161
Total Acres
30 miles+/-
Parcel #
numerous
State Highways
SR89, SR28, SR267, I-80
Railways
Union Pacific
Airports
Truckee-Tahoe
Schools
N. Tahoe/Truckee
Waterways
Lake Tahoe, Truckee River, Griff Creek, other creeks
Other Location Info
Douglas County
Notice of Determination
Approving Agency
CA Public Utilities Commission
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes