Alpaugh K-12 Reconstruction Project

3 Documents in Project

Summary

SCH Number
2012031076
Lead Agency
Alpaugh Unified School District (AUSD)
Document Title
Alpaugh K-12 Reconstruction Project
Document Type
NOD - Notice of Determination
Received
Posted
8/15/2017
Present Land Use
Existing school site and vacant District-owned land in the Alpaugh Urban Boundary, zoned Rural Residential
Document Description
DTSC approved the Removal Action Workplan (RAW) for the project. The objective of the RAW is to mitigate potential risk to human health and environment by excavation and offsite disposal of approx. 480 bank cubic yards of soil containing concentrations of organochlorine pesticides exceeding unrestricted land use cleanup goals. The MND analyzed the Alpaugh Unified School District's proposal to redevelop the existing school site in two phases to support a Master Plan Capacity of up to 1,100 students and 25 classrooms in grades K-12. Phase 1 would consist of construction of the new classroom buildings and two computer labs. The school library and administration services would also be located on the ground floor. Phase 2 would consist of the construction of a new gymnasium and multipurpose/cafeteria building.

Contact Information

Name
Craig Sanchez
Agency Name
DTSC
Contact Types
Lead/Public Agency

Location

Counties
Tulare
Cross Streets
Road 39/Avenue 54
Zip
93201
Total Acres
18
Parcel #
311-23-001, -24-015, -018,-024 > -031
State Highways
No
Railways
West Isle Line
Airports
No
Schools
AUSD onsite programs
Waterways
Deer Creek, multiple canals
Township
23S
Range
23E
Section
33
Base
MDB&M
Other Location Info
City/Nearest Community: Alpaugh

Notice of Determination

Approving Agency
DTSC
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print