Mill Creek Watershed Young Forest Restoration Plan

2 Documents in Project

Summary

SCH Number
2012022010
Lead Agency
California Department of Parks and Recreation
Document Title
Mill Creek Watershed Young Forest Restoration Plan
Document Type
NOD - Notice of Determination
Received
Posted
4/25/2012
Present Land Use
State Park - Recreational
Document Description
The Department of Parks and Recreation proposes to restore young forests (11-24 years old) by mechanically thinning (using chainsaws) approximately 941 hectares (3,325 acres) of formerly harvested stands to promote historic species composition, encourage rapid tree growth, and accelerate the development of late-seral forest characteristics. The project is located in the Mill Creek Watershed of Del Norte Coast Redwoods State Park. A minimum of 185 trees per hectare (tph) (75 trees per acre (tpa)) will be retained after restoration and most stands will have at least 370 tph (150 tpa) retained. Prescriptions may be modified when necessary to protect sensitive resources such as rare plants or animals, wetlands habitats, cultural resources, and geologically unstable areas.

Contact Information

Name
John E. Harris
Agency Name
California Department of Parks and Recreation
Contact Types
Lead/Public Agency

Location

Cities
Crescent City
Counties
Del Norte
Cross Streets
Hamilton Road and Hwy 101
Zip
95531
Total Acres
2325
State Highways
Hwy 101
Waterways
Mill, Rock, Williamson, Hunter and Tuwar Creek
Township
15N
Range
1W
Section
1-36
Base
HB&M

Notice of Determination

Approving Agency
California Department of Parks and Recreation
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print