Archer Forward: Campus Prservation and Improvement Plan - Phase I Haul Route
5 Documents in Project
Summary
SCH Number
2012011001
Lead Agency
City of Los Angeles
Document Title
Archer Forward: Campus Prservation and Improvement Plan - Phase I Haul Route
Document Type
NOD - Notice of Determination
Received
Posted
6/27/2017
Present Land Use
Private school serving grades 6-12 / Z: RE11-1 & R3-1 / Very Low II Residential, Medium Residential
Document Description
On August 4, 2015, the City of Los Angeles approved the Archer Forward: Campus Preservation and Improvement Plan project (Case No. CPC-1014-666-VCU-ZAA-SPR; 2011-2689-EIR). The Archer Forward project consists of improvements to the existing Archer campus totaling 60,721 sq. ft. of new development, including the replacement of the existing 30,071 sq. ft. North Wing of the Main Building with a 30,400 sq. ft. renovated North Wing, and the development of an approx. 39,330 sq. ft. Multi-purpose Facility, a 17,758 sq. ft. Performing Arts Center, and a 7,400 sq. ft. Visual Arts Center. The existing outdoor athletic field would be improved to include a regulation-size soccer and softball field. Parking would be provided in a new underground parking structure located below the athletic field to accommodate 164 parking spaces, expandable to 251 parking spaces with the use of an attendant. The two adjacent properties currently owned by Archer, 11728 West Chaparal Street and 141 North Barrington Avenue, would be removed to accommodate the project. A portion of 141 North Barrington Avenue, referred to as the Residential Portion of the Barrington Parcel, would remain a residential use in accordance with Section 12.07.01 of the LA Municipal Code. At full build-out, the campus' total development would be 148,995 sq. ft., and 75 percent of the campus would be open space. The EIR for the Archer Forward project analyzed primary and alternative haul routes of for the export associated with the project.
Contact Information
Name
Krikor Manoukian
Agency Name
City of Los Angeles, Building and Safety Dept.
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Cities
Los Angeles, Los Angeles, City of
Counties
Los Angeles
Cross Streets
Sunset Boulevard and Barrington Avenue
Zip
90049
Total Acres
7.31
Parcel #
4402009-013/ 014/ 016/ 002/ 003
State Highways
I-405
Schools
Several
Other Location Info
Brentwood-Pacific Palisades
Notice of Determination
Approving Agency
City of Los Angeles Dept. of Building & Safety
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.