Comanche Creek Greenway Improvement Project

4 Documents in Project

Summary

SCH Number
2011122062
Lead Agency
Chico, City of (City of Chico)
Document Title
Comanche Creek Greenway Improvement Project
Document Type
NOD - Notice of Determination
Received
Posted
2/1/2012
Present Land Use
Open Space/OS1, OS2 / Primary Open Space and Secondary Open Space

Document Description
To construct an approx. 6.7-mile long bicycle facilities project generally along the east side of the SR 99 corridor over two phases. The bikeway is a combination of Class l/ll/lll facilities commencing at Eaton Road to the north and traversing south to Southgate Avenue. The bikeway will be located on surface streets, drainage easements, Butte County owned SUDAD Ditch, and City park land, Associated safety devices, including lighting, fencing, controlled crossings and median refuges, will be incorporated when appropiate.

Contact Information
Meredith Williams
City of Chico
P.O. Box 3420
Chico, CA 95927

Phone : (530) 879-6813

Location

Coordinates
39°42'36"N 121°49'12"W
Cities
Chico
Counties
Butte
Cross Streets
Midway and East Park Avenue
Zip
95928
Total Acres
29.6
Parcel #
039-420-001, -620-028, -060-021, 041
State Highways
Hwy 99 and 32
Railways
UPRR
Airports
No
Schools
Chico Cntry Day, CSUC
Waterways
Comanche Creek, Little and Big Chico Creeks, Crouch Ditch
Township
21
Range
1E
Base
MDB&M

Notice of Determination

Approving Agency
City of Chico
Approving Agency Role
Lead Agency
Approved On
Final Environmental Document Available at
City of Chico Municipal Building, 411 Main Street, 2nd Floor, Chico, CA 95928

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.