Cabin Creek Biomass Facility Project (at Eastern Regional MRF and Transfer Station site)
7 Documents in Project
Summary
SCH Number
2011122032
Lead Agency
Placer County
Document Title
Cabin Creek Biomass Facility Project (at Eastern Regional MRF and Transfer Station site)
Document Type
NOD - Notice of Determination
Received
Posted
12/26/2012
Present Land Use
Placer County General Plan: Agricultural/Timberland - 80 Acre Minimum; Zoning: forestry-special purpose (FOR-SP)
Document Description
Placer County is proposing to construct a two-megawatt wood-to-energy biomass facility that would use gasification technology at the Eastern Regional Materials Recovery Facility (MRF) and Landfill. The project site is located on 3.7-acre site in the southernmost area of the property. The proposed project would include construction of an approximately 11,000 sf, two-story structure to house the power generating and emissions control equipment, an approximately one-acre material storage area including a 7,000 sf open air pole barn structure, and additional onsite improvements to support operations at the facility. Biomass materials (fuel) would be processed (ground and screened) at locations from which they are removed (e.g. USFS fuels reduction sites) and delivered via haul truck to the proposed project site.
Contact Information
Name
Maywan Krach
Agency Name
Placer County Community Development Resource Agency
Contact Types
Lead/Public Agency
Phone
Location
Cities
Truckee
Counties
Placer
Cross Streets
SR 89/Cabin Creek Road
Zip
96161
Parcel #
080-070-016
State Highways
SR 89
Waterways
Truckee River
Township
17N
Range
16E
Section
28
Base
MDB&M
Notice of Determination
Approving Agency
Placer County
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.