Use Permit Application No. 2011-11 - Beltran Ranch Solar Facility
4 Documents in Project
Summary
SCH Number
2011112013
Lead Agency
Stanislaus County
Document Title
Use Permit Application No. 2011-11 - Beltran Ranch Solar Facility
Document Type
NOD - Notice of Determination
Received
Posted
4/24/2013
Present Land Use
PLU: Fallow/Orchard
Z: A-2-40 & A-2-160
GPD: Agriculture
Document Description
Request to establish a 140 megawatt solar photovoltaic facility on 606 acres of a 1,720 acre site. Additional site improvements include all weather fire access roads; maintenance building; security fencing; construction staging area; office trailer; sheds; substation. A 30 foot high overhead power line will be added to the existing above ground power lines to connect the solar facility to the substation. A transmission interconnect to PG&E's existing Salado-Newman transmission line will also be added. Use Permit 2010-09 was approved on November 4, 2010, to occupy 382 acres of this site.
Contact Information
Name
Rachel Wyse
Agency Name
Stanislaus County
Contact Types
Lead/Public Agency
Phone
Location
Cities
Newman
Counties
Stanislaus
Cross Streets
I-5
Zip
95360
Total Acres
606
Parcel #
025-017-019, 026-012-003, 027-017-063, 077, 080, 082
State Highways
I-5
Airports
Crows Landing Air Facility
Waterways
CA Aqueduct
Township
6, 7
Range
7, 8
Section
35/36
Base
MDB&M
Other Location Info
City/Nearest Community: Crows Landing
Other Information
Section Cont.: 36-6-7., 30/31-6-8, 1-7-7
Notice of Determination
Approving Agency
Stanislaus County Planning Comm.
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.