Alamitos Pumping Plant Force Main No. 2

3 Documents in Project

Summary

SCH Number
2011111040
Lead Agency
Los Angeles County Sanitation District
Document Title
Alamitos Pumping Plant Force Main No. 2
Document Type
NOD - Notice of Determination
Received
Posted
11/19/2012
Present Land Use
Sewage Pumping Plant, Public and Private Right of Way
Document Description
Project will provide a relief sewer as a backup system to the existing Alamitos Pumping Plant Force Main to comply with the USEPA Order of March 2004, to reduce sanitary sewer overflows (SSOs) and to commit to pipe rehabilitation, pump station upgrades, and capacity assurance measures. The Project will involve construction of approximately 2,200 feet of 10-inch diameter high-density polyethylene (HDPE) force main sewer and appurtenant structures to provide redundancy for the existing Alamitos Pumping Plant Force Main. The Project will be sized to match the capacity of the existing force main, and discharge to a nearby sewer with sufficient capacity.

Contact Information

Name
Susan Stewart
Agency Name
State Water Resources Control Board
Contact Types
Lead/Public Agency

Location

Cities
Long Beach, Signal Hill
Counties
Los Angeles
Cross Streets
Alamitos Avenue and East 20th Street
Zip
90755
Total Acres
.04
Parcel #
721-500-9900
State Highways
CA-1, 19, I-710, 405
Railways
Metro Blue Line
Airports
Long Beach
Waterways
Los Angeles River

Notice of Determination

Approving Agency
State Water Board
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print