A Revised Solid Waste Facilities Permit for East Stockton Recycling and Transfer Station, Facility No. 39-AA-0018, in the City of Stockton, San Joaquin County
2 Documents in Project
Summary
SCH Number
2011102023
Lead Agency
City of Stockton
Document Title
A Revised Solid Waste Facilities Permit for East Stockton Recycling and Transfer Station, Facility No. 39-AA-0018, in the City of Stockton, San Joaquin County
Document Type
NOD - Notice of Determination
Received
Posted
5/18/2012
Present Land Use
Processing of recyclable construction and demolition wastes; truck parking and storage/IL & IG/ Industrial
Document Description
The proposed SWFP revision under consideration includes the following changes: an increase in tonnage from 512 tpd to 1,000 tpd; an increase in hours of operation from Monday-Friday 7:30 a.m. - 5:00 p.m., Saturdays 8:00 a.m. - 12:00p.m. to ancillary operations that will be allowed 24 hours per day, seven days a week, receipt of materials will be allowed: Monday - Friday 5:00 a.m. to 10:00 p.m., Saturday - Sunday 6:00 a.m. to 5:00 p.m.; allow an increase in permitted traffic volume from 78 vehicles per day to 410 vehicles per day; the addition of a 33,000 square foot material recovery building; and the addition of new equipment.
Contact Information
Name
Joy Isaacson
Agency Name
Cal Recycle
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Cities
Stockton
Counties
San Joaquin
Cross Streets
Weber Avenue/Filbert Street
Zip
95205
Total Acres
6.73
Parcel #
153-180-04, 06, 08, 55 & 153-231-01, 17
State Highways
Hwy 4, 99
Railways
ST&E, BNSF
Schools
Fremont & Fillmore ES
Waterways
Mormon Slough; Stockton Diverting Canal
Township
1N
Range
7E
Section
2
Base
MDB&M
Notice of Determination
Approving Agency
CalRecycle
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A