The Project will consist of the development of a 750-megawatt (MW) photovoltaic (PV) solar energy generating facility in two units and a 13.2 mile double-circuit 230-kilovolt generation-tie transmission line. Unit 1 will be located on the eastern side of the solar plant site and would generate up to 250-MW of power on 2,259 acres, Unit 2 will be located on the western side and would generate up to 500-MW of power on 2,178 acres. The linear facilities (include Phase l) will be located on 136.2 acres for a total of 4,573.2 acres. The Project will result in impacts to 4,532.9 acres of desert tortoise (Gopherus agassizi) habitat. The project is expected to result in incidental take or desert tortoise, which is designated as a threatened species under California Endangered Species Act (CESA). The ITP referenced above as issued by CDFW authorizes incidental take of species listed under CESA that may occur as a result of Project implementation.

Contact Information

Name
Magdalena Rodriguez
Agency Name
Department of Fish and Wildlife
Contact Types
Lead/Public Agency

Location

Cities
Blythe, Riverside
Counties
Riverside
Cross Streets
North of Interstate 10, Black Rock Road
Zip
92225
Total Acres
4573
Parcel #
812-130-006,-007,-008;818-210-014, etc.
State Highways
Hwy 95
Railways
Union Pacific
Airports
Blythe
Schools
Palo Verde Valley Unified
Waterways
McCoy Wash
Township
5S
Range
21E
Section
36
Base
SBB&M

Notice of Determination

Approving Agency
Department of Fish and Wildlife
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA