CR&R Green Energy Facility, Perris, Major Modification 11-04-0001

4 Documents in Project

Summary

SCH Number
2011091080
Lead Agency
City of Perris
Document Title
CR&R Green Energy Facility, Perris, Major Modification 11-04-0001
Document Type
NOD - Notice of Determination
Received
Posted
11/29/2011
Present Land Use
Materials Recovery Facility (MRF) - Transfer Station / General Industrial
Document Description
Major Modification 11-04-0001 to CUP 91-27 will allow expansion of the CR&R Perris Materials Recovery Facility (MRF) to include the 6.8 acre Green Energy Facility with one anaerobic digester, biofilter, supporting equipment and biofuel dispensing area. The first phase of the project anticipates conversion of up to 150 tons of processed organic municipal waste into biogas and compostable material per day, with conversion of up to 450 tons in future phases. Methane gas is a natural byproduct of the anaerobic process. After refining, methane is a high grade natural gas that will be refined and piped underground to the on-site RNG station with slow-fill fueling pumps for use by 48 CR&R collection trucks.

Contact Information

Name
Diane Sbardellati
Agency Name
City of Perris
Contact Types
Lead/Public Agency

Location

Cities
Perris
Counties
Riverside
Cross Streets
Ellis Avenue & Goetz Road
Zip
92570
Total Acres
6.8
Parcel #
330-030-019, 018, 017, 014, 003
State Highways
Hwy 74
Railways
AT&SF
Airports
Perris Valley
Schools
Perris Lake HS, Pinacate MS, Railway ES
Waterways
San Jacinto River

Notice of Determination

Approving Agency
Perris Planning Commission
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print