CA Endangered Species Act (CESA) Incidental Take Permit (ITP) No. 2081-2012-048-06

9 Documents in Project

Summary

SCH Number
2011091055
Lead Agency
Inyo County
Document Title
CA Endangered Species Act (CESA) Incidental Take Permit (ITP) No. 2081-2012-048-06
Document Type
NOD - Notice of Determination
Received
Posted
11/25/2013
Present Land Use
The site is largely open space, but includes a cartaker's residence, roadway, and ancillary uses / OS-40 & RR-1.0 / RP & RRH
Document Description
The Project would develop a spring water bottling facility and ancillary uses. The water bottling facility would include an approximately 198,500-square-foot bottling plant facility with four bottling lines an approximately 40,000-square-foot storage warehouse. Proposed ancillary uses include rooftop solar array, a fire suppression building, a stormwater detention basin, a leach mound, a fire access road, and a parking and truck, staging area. To provide adequate access from US 395 to the bottling facility, the Project would remove the site's existing access road (i.e., Cabin Bar Ranch Road) and construct a new permanent access road approximately 2,500 feet to the south. The bottling facility would utilize spring water from three existing production wells to supply the bottling operations. The Project would also use fourth existing well to provide domestic potable water to the water bottling facility's employees.

Contact Information

Name
Kimberly Nicol
Agency Name
Department of Fish and Wildlife (CDFW)
Contact Types
Lead/Public Agency

Location

Counties
Inyo
Cross Streets
US 395 / Cabin Bar Ranch Road
Zip
93549
Total Acres
43.24
Parcel #
Multiple
State Highways
US 395
Railways
Southern Pacific
Waterways
Cartago Creek, Owens Dry Lake
Township
19S
Range
37,36E
Section
1, 5,6
Base
MtDiablo
Other Location Info
Cartago

Notice of Determination

Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print