SW GJ 1036 PPA

23 Documents in Project

Summary

SCH Number
2011091045
Lead Agency
City of San Diego
Document Title
SW GJ 1036 PPA
Document Type
NOD - Notice of Determination
Received
Posted
3/23/2022
Document Description
The AC Water and Sewer Group would include replacement of a total of 10,705 linear feet (LF) of water mains and 2,721 LF of sewer mains. Approximately 10,705 LF of existing 6-, 8- and 12-inch Asbestos Cement (AC) water main will be replaced-in-place with new 8- and 12-inch polyvinyl chloride (PVC) water main within the same trench at the same or shallower depth. Approximately 565 LF of existing 8-inch vitrified clay (VC) and clay pipe (CP) sewer main will be replaced-in-place in the same trench alignment at the same or shallower depth with new 8-lnch PVC sewer main. Approximately 1286 LF of PVC sewer main will be replaced in place within the same trench, but deeper than the existing depth with new PVC main sewer mains at depths ranging from 8 to 12 feet. Approximately 779 LF of new 8-inch PVC sewer main and 91 LF of new 10-inch PVC sewer main will be installed in new alignments at depths ranging from 8 to 12 feet via open trench construction.

Contact Information

Name
Courtney Holowach
Agency Name
City of San Diego
Job Title
Planner
Contact Types
Lead/Public Agency

Location

Cities
San Diego
Counties
San Diego
Regions
Citywide
Other Information
Sewer Main and Water Main Replacement Program

Notice of Determination

Approving Agency
City of San Diego
Approving Agency Role
Lead Agency
Approved On
County Clerk
San Diego
Final Environmental Document Available at
Development Department Services, 1222 First Avenue, San Diego, CA 92101

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
Yes (An Addendum to Negative Declaration)
(3) Mitigated measures were made a condition of the approval of the project
N/A
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A

Attachments

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613. For more information, please visit OPR’s Accessibility Site.

Download CSV New Search Print