Southport Early Implementation Project
18 Documents in Project
Summary
SCH Number
2011082069
Lead Agency
West Sacramento Area Flood Control Agency
Document Title
Southport Early Implementation Project
Document Type
NOD - Notice of Determination
Received
Posted
8/3/2016
Present Land Use
Agricultural
Document Description
To construct levee improvements on the west levee of the Sacramento River from station 0+99 to 290+79 including 1.8 miles of strengthen-in-place improvements; 3.7 miles of setback levee; remediate 3.9 miles of deficient existing (remnant) levee; 5.4 miles of cutoff wall construction; installation of 3.0 miles of seepage berms; installation of rock revetment in locations identified with a high erosion potential on the new setback levee alignment and along the remnant levee in areas where the new setback levee will be constructed; demolition of Pumping Plant No. 5; and removal of existing utilities and encroachments that do not comply with Title 23 Standards or require relocation.
Contact Information
Name
Stephanie Tadlock
Agency Name
Central Valley Regional Water Board
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Cities
West Sacramento
Counties
Yolo
Cross Streets
Jefferson Blvd. at West Sacramento City limits
Zip
95691
Total Acres
119
Parcel #
044-020-02
State Highways
84
Waterways
Sacramento River, Deep Water Ship Channel
Township
8N
Range
4E
Section
31
Notice of Determination
Approving Agency
Central Valley Regional Water Board
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.