Village Parkway Project

17 Documents in Project

Summary

SCH Number
2011082069
Lead Agency
West Sacramento Area Flood Control Agency
Document Title
Village Parkway Project
Document Type
NOD - Notice of Determination
Received
Posted
7/25/2016
Present Land Use
Agricultural

Document Description
To construct levee improvements on the west levee of the Sacramento River from station 0+99 to 290+79 including 1.8 miles of strengthen-in-place improvements; 3.7 miles of setback levee; remediate 3.9 miles of deficient existing (remnant) levee; 5.4 miles of cutoff wall construction; installation of 3.0 miles of seepage berms; installation of rock revetment in locations identified with a high erosion potential on the new setback levee alignment and along the remnant levee in areas where the new setback levee will be constructed; demolition of Pumping Plant No. 5; and removal of existing utilities and encroachments that do not comply with Title 23 Standards or require relocation.

Contact Information
James Herota
Central Valley Flood Protection Board
3310 El CAmino Ave., Suite 170
Sacramento, CA 95821

Phone : (916) 574-0651

Location

Coordinates
38°30'08.1"N 121°34'55.3"W
Cities
West Sacramento
Counties
Yolo
Cross Streets
Jefferson Blvd. at West Sacramento City limits
Zip
95691
Total Acres
119
Parcel #
044-020-02
State Highways
84
Waterways
Sacramento River, Deep Water Ship Channel
Township
8N
Range
4E
Section
31

Notice of Determination

Approving Agency
Central Valley Flood Protection Board
Approving Agency Role
Responsible Agency
Approved On
Final Environmental Document Available at
3310 El CAmino Ave., Suite 170, Sacramento, CA 95821

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.