Congeneration Plant Replacement Project Phase 1

4 Documents in Project

Summary

SCH Number
2011082037
Lead Agency
University of California
Document Title
Congeneration Plant Replacement Project Phase 1
Document Type
NOD - Notice of Determination
Received
Posted
12/12/2011
Present Land Use
Campus Support (under the UC Santa Cruz 2005 Long Rnage Development Plan)
Document Description
The proposed project is the replacement of the Campus' existing cogeneration equipment with a new, 4.2 megawatt (MW) natural gas-fueled combustion turbine generator (CTG). The project is would enable the Campus to meet a greater proportion of the backup needs of the existing buildings in the central campus and the Biomedical Sciences Facility, which is currently under construction. The equipment would be installed in a new, system to accommodate the additional electricity production capacity of the new system and to allow for efficient switching on of backup power to new and/or different facilities. The project would require improvements to the natural gas supply to the campus to improve the reliability of pressure in the gas line that serves the cogeneration plant.

Contact Information

Name
Sally Morgan
Agency Name
University of California, Santa Cruz
Contact Types
Lead/Public Agency

Location

Cities
Santa Cruz
Counties
Santa Cruz
Cross Streets
McLaughlin Drive/Heller Drive
Zip
95064
Total Acres
.4
Parcel #
001-011-13
State Highways
Hwy 1, 17, 9
Schools
Westlake ES
Waterways
Jordan Gulch
Township
11S
Range
2W
Base
MDB&M

Notice of Determination

Approving Agency
University of California
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.