Outfall Land Section and Ocean Outfall Booster Pump Station Piping Rehabilitation

4 Documents in Project

Summary

SCH Number
2011081022
Lead Agency
Orange County Sanitation District
Document Title
Outfall Land Section and Ocean Outfall Booster Pump Station Piping Rehabilitation
Document Type
NOD - Notice of Determination
Received
Posted
2/24/2012
Present Land Use
General Plan: P, OS-C, OS-S, OS-W Z: IL, CC, OS, OS-WR
Document Description
Note: FYI FINAL The proposed project consists of inspection, condition assessment, and rehabilitation of corrosion damage components of the land section of the existing 120-inch diameter, primary five-mile outfall (Long Outfall) System within the Sanitation District's Treatment Plant 2 to a Beach Box located on Huntington State Beach. The five project elements for the Long Outfall System rehabilitation are: the Surge Tower 2, land section of Long Outfall, abandonment of metering ports and vaults, replacement of existing effluent flow meter and rehabilitation of Beach Box. To take a portion of the land side of the Long Outfall System out of service, two alternatives are considered, one to construct a bypass and continue use of the Long Outfall or divert flow to an 1-mile emergency outfall.

Contact Information

Name
Rob Thompson
Agency Name
Orange County Sanitation District
Contact Types
Lead/Public Agency

Location

Cities
Huntington Beach
Counties
Orange
Cross Streets
Brookhurst Street, Pacific Coast Hwy, Huntington State Beach, Santa Ana River
Zip
92646
Total Acres
110
Parcel #
114-160 (7, 42, 72)
State Highways
Pacific Coast Hwy 1
Airports
John Wayne
Schools
Eader ES, Edison HS
Waterways
Santa Ana River, Pacific Ocean
Township
6S
Range
10W
Section
30

Notice of Determination

Approving Agency
Orange County Sanitation District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA