Consolidation Cell Removal - Georgia-Pacific Fort Bragg Mill Site

2 Documents in Project

Summary

SCH Number
2011072058
Lead Agency
Department of Toxic Substances Control
Document Title
Consolidation Cell Removal - Georgia-Pacific Fort Bragg Mill Site
Document Type
NOD - Notice of Determination
Received
Posted
9/1/2011
Present Land Use
Industrial
Document Description
The DTSC is proposing to approve an Explanation of Significant Differences (ESD) that would modify the final remedy for Operable Unit A (OU-A) contained in a Remedial Action Plan previously approved by DTSD in August 2008. If approved, it would allow for the removal of approximately 13,850 cy of contaminated soils, waste, and debris (approximately 756 truck loads) from a previously constructed consolidated cell located at the former Georgia-Pacific Wood Products Facility; and transporting the material to an approved disposal facility. After removal activities have been completed, the resulting excavated area will be backfilled with 10,000 cy of clean fill material available at the Georgia-Pacific site. If more fill material are needed, it will be obtained from the Noyo Harbor Dredge Sands.

Contact Information

Name
Thomas Lanphar
Agency Name
Department of Toxic Substances Control
Contact Types
Lead/Public Agency

Location

Cities
Fort Bragg
Counties
Mendocino
Cross Streets
Redwood Avenue and Main Street
Zip
95437
Total Acres
417
Parcel #
008-430-01 & 008-430-02
State Highways
Hwy 1
Railways
CA Western RR
Schools
4
Waterways
Noyo River and Pudding Creek

Notice of Determination

Approving Agency
DTSC
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.