Concurrence in the Issuance of a New Full Solid Waste Facilities Permit for Altamont Landfill & Resource Recovery Facility, Compostable Materials Handling Facil

3 Documents in Project

Summary

SCH Number
2011072021
Lead Agency
Alameda County
Document Title
Concurrence in the Issuance of a New Full Solid Waste Facilities Permit for Altamont Landfill & Resource Recovery Facility, Compostable Materials Handling Facil
Document Type
NOD - Notice of Determination
Received
Posted
7/7/2017
Present Land Use
Site presently used as solid waste disposal facility/ A , Zoning/ Large Parcel Agriculture General Plan Designation
Document Description
Within the boundaries of Altamont Landfill and Resource Recovery Facility, the proposed project will be a Composting Material Handling Facility that will use Covered Aerated Static Pile (CASP) technology to receive, process and compost up to 500 tons per day of materials such as green materials, clean dimensional lumber, agricultural materials, food waste, organics diverted from municipal solid waste, and digestate from anaerobic organics operations; permitted hours of operation will be Monday - Friday 6:00 AM to 4:00 PM for the public, Monday - Sunday 24 hours of commercial haulers, Monday - Sunday 24 hours for ancillary operations; and a permitted area of 60.5 acres.

Contact Information

Name
Jeffery Esquivel
Agency Name
CalRecycle
Contact Types
Lead/Public Agency

Location

Cities
Livermore
Counties
Alameda
Cross Streets
10840 Altamont Pass Road
Zip
94551
Total Acres
2170
Parcel #
99B-6225-1, 99B-6062-5, 99B-6275
State Highways
I-580
Railways
Along southern border
Airports
No
Schools
No
Waterways
Bethany Reservoir State Park
Township
2S
Range
3E
Section
16,17,
Other Information
Continue Section: & 21

Notice of Determination

Approving Agency
CalRecycle
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print