Alta East and Northern Portion of Alta Infill II Wind Energy Project; CA Endangered Species Act Incidental Take Permit No. 2081-2013-016-04 (ITP)

19 Documents in Project

Summary

SCH Number
2011071051
Lead Agency
Kern County
Document Title
Alta East and Northern Portion of Alta Infill II Wind Energy Project; CA Endangered Species Act Incidental Take Permit No. 2081-2013-016-04 (ITP)
Document Type
NOD - Notice of Determination
Received
Posted
5/24/2013
Present Land Use
Various
Document Description
The project involves the construction and installation of up to 115 wind turbine generators (WTGs) and supporting infrastructure to operate the WTGs as a wind power generation facility. Major components of the project include two permanent and three temporary meteorological towers, 26.24 miles of access roads, fencing, clearing and grading, underground communication cables, underground and overhead collection systems, overhead transmission lines, one collector substation, up to three concrete batch plants, one laydown area, two aqueduct bridge crossings, one operations and maintenance (O&M) facility, and O&M activities.

Contact Information

Name
Lori Bono
Agency Name
CDFW
Contact Types
Lead/Public Agency

Location

Cities
Mojave, Tehachapi
Counties
Kern
Cross Streets
2 miles west of the intersection of Hwy 58 and Hwy 14
Zip
93501
Total Acres
2,592
Parcel #
Multiple
State Highways
SR 58 & 14
Railways
Union Pacific
Airports
Mojave
Schools
Mountain View Cont.
Waterways
Los Angeles Aqueduct
Township
mult.
Range
mult.
Section
mult.
Base
SBB&M

Notice of Determination

Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print