(Project File No. PLN11-089)

4 Documents in Project

Summary

SCH Number
2011062042
Lead Agency
City of Richmond
Document Title
(Project File No. PLN11-089)
Document Type
NOD - Notice of Determination
Received
Posted
7/30/2014
Present Land Use
M-3 (Heavy Industrial)
Document Description
The Modernization Project Preffered Alternative (Alternative 11) would complete construction and begin operation of a replacement Hydrogen Plant Replacement and a collection of new equipment improvements that remove naturally occurring sulfur contained in feedstocks processed at the Facility (collectively, the Sulfur Removal Improvements). The Project would also construct related infrastructure improvements to Facility piping, utility lines, and electrical systems. The Project also includes several integral equipment components that would reduce air emissions from Facility operations (the Emission Reduction Project Components) and further Project Design Features proposed to avoid or minimize environmental impacts. The Project includes a restriction of the Refinery's future physical Greenhouse gas emissions so as to not exceed the average baseline level (4,602,947 MT/yr.) and would also limit the sulfur removal to 750 long tons per day.

Contact Information

Name
Lina Velasco
Agency Name
City of Richmond
Contact Types
Lead/Public Agency

Location

Cities
Richmond
Counties
Contra Costa
Cross Streets
Chevron Way, Castro Street
Zip
94804
Total Acres
2153
Parcel #
Multiple
State Highways
I-580
Railways
BNSF
Schools
Multiple
Waterways
San Pablo Bay / San Francisco Bay

Notice of Determination

Approving Agency
City of Richmond City Council
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.