Santa Monica Pier Emergency Gangway and Phase 4 Structural Upgrade project

3 Documents in Project

Summary

SCH Number
2011061047
Lead Agency
City of Santa Monica
Document Title
Santa Monica Pier Emergency Gangway and Phase 4 Structural Upgrade project
Document Type
NOD - Notice of Determination
Received
Posted
9/2/2011
Present Land Use
GP: Beach and Oceanfront District Z: Residential-Visitor Commercial
Document Description
There are two distinct components of the proposed project: the emergency gangway and floating dock, and the Phase 4 structural upgrades. The proposed emergency gangway and floating dock component consists of: 1) demolition and removal of one existing concrete pile and an 18-foot-long by 8-foot-wide section of the concrete decking of the southern fishing platform; 2) installation of a 2.5-ton capacity hydraulic crane lift on the pier; 3) construction, transportation, and anchoring of a 60-foot-long by 36-foot-wide floating barge (dock) on the south side of the pier (anchoring will be with 12 screw-type anchors or piles driven into the seafloor in approximately 16 feet of water [MLLW]); 4) installation of a 88-foot-long by 5-foot-wide aluminum gangway on the south side of the pier; 5) installation of various railings, utilities, and amenities at the project site; and; 6) demobilization and removal of construction equipment and site cleanup.

Contact Information

Name
Eric Bailey
Agency Name
City of Santa Monica
Contact Types
Lead/Public Agency

Location

Cities
Santa Monica
Counties
Los Angeles
Cross Streets
Colorado Boulevard/Appian Way
Zip
90401
Total Acres
<1
Parcel #
4290-023-901, 902
State Highways
I-10, SR-1
Railways
No
Airports
Santa Monica Municipal
Schools
Numerous
Waterways
Pacific Ocean

Notice of Determination

Approving Agency
City of Santa Monica
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.

Download CSV New Search Print