Feather River West Levee Project (California Endangered Species Act Incidental Take Permit (ITP) No. 2081-2013-054-02).

36 Documents in Project

Summary

SCH Number
2011052062
Lead Agency
Sutter Butte Flood Control Agency
Document Title
Feather River West Levee Project (California Endangered Species Act Incidental Take Permit (ITP) No. 2081-2013-054-02).
Document Type
NOD - Notice of Determination
Received

Document Description
Note: Extended Review Per lead The Sutter Butte Flood Control Agency (SBFCA) is proposing the Feather River West Levee Project (FRWLP) to reduce flood risk in the Sutter Basin, which includes portions of Sutter and Butte Counties. The project area for the FRWLP is focused on the corridor along the west levee of the Feather River from Thermalito Afterbay on the north to approximately 4 miles north of the confluence with the Sutter Bypass on the south. This corridor is roughly 500 feet toward the land side of the existing levees and 100 feet toward the water side. This corridor was determined as the area in which levee improvements, such as seepage berms, stability berms, relief wells, setback levees, erosion protection, and slurry cutoff walls, are likely to occur. The corridor is approximately 41 miles long. The project area would also include borrow/spoil sites or project mitigation sites outside of this corridor.

Contact Information
Mike Inamine
Sutter Butte Flood Control Agency
1227 Bridge Street, Suite C
Yuba City, CA 95991

530 740 2448
inorgaard@icfi.com

Location

Coordinates
39°8'25.56"N 121°37'.9624"W
Cities
Yuba City Live Oak Gridley Biggs
Counties
Sutter Butte
Cross Streets
Numerous
Zip
Numerous
Total Acres
1000
Parcel #
Numerous
State Highways
Hwy 99
Railways
UPRR
Airports
Butte County
Schools
Numerous
Waterways
Feather River

Notice of Determination

Approving Agency
Sutter Butte Flood Control Agency
Approving Agency Role
Lead Agency
Approved On
Final EIR Available Location
Sutter County, 1160 Civic Center Blvd., Yuba City, CA 95993

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A Statement of Overriding Considerations was adopted for this project
Yes
(5) Findings were made pursuant to the provisions of CEQA
Yes