Feather River West Levee Project, Gridley Bridge Erosion Site Repair (Streambed Alteration Agreement No. 1600-2016-0054-R2)

67 Documents in Project

Summary

SCH Number
2011052062
Lead Agency
Sutter Butte Flood Control Agency (SBFCA)
Document Title
Feather River West Levee Project, Gridley Bridge Erosion Site Repair (Streambed Alteration Agreement No. 1600-2016-0054-R2)
Document Type
NOD - Notice of Determination
Received
Posted
7/14/2016
Present Land Use
n/a
Document Description
CDFW has executed Streambed Alteration Agreement No. 1600-2016-0054-R2, pursuant to section 1602 of the Fish and Game Code to the project Applicant, Sutter Butte Flood Control Agency, (the Permittee), as represented by Michael Bessette. The proposed project would repair two erosion sites by placing rock slope protection (RSP) along the waterside of the levee. RSP is placed along the slope of the levee to prevent scour or erosion of the river bed and levee slope. RSP would be placed in layers, would include a bedding layer above the water, and would be comprised of angular rock that interlocks together to form a protective armor over the levee slope. RSP placement will be accomplished either from the top of the levee or, alternatively, material may be placed from a barge using typical construction equipment such as an excavator/front-end loader. Material may be stockpiled onsite then transported by barge between the erosion repair site south of East Gridley Road and the erosion repair site norht of East Gridley Road.

Contact Information

Name
Kursten Sheridan
Agency Name
CDFW
Contact Types
Lead/Public Agency

Location

Counties
Sutter
Cross Streets
East Gridley Road / Feather River and Laurel Avenue / Feather River
State Highways
Hwy 99, 70
Waterways
Feather River

Notice of Determination

Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print