Feather River West Levee Project (Contract B Levee Improvements SAA# 1600-2014-0001-R2
67 Documents in Project
Summary
SCH Number
2011052062
Lead Agency
Sutter Butte Flood Control Agency
(SBFCA)
Document Title
Feather River West Levee Project (Contract B Levee Improvements SAA# 1600-2014-0001-R2
Document Type
NOD - Notice of Determination
Received
Posted
4/21/2014
Document Description
The California Department of Fish and Wildlife is executing Streambed Alteration Agreement Number 1600-2014-0001-R2 pursuant to Section 1602 of the Fish and Game Code to the project applicant, Sutter Butte Flood Control Agency.
The Project consists of degrading the Feather River West Levee to construct a slurry cutoff wall, constructing a deep cutoff wall inside the levee prism wall, backfilling landslide toe depressions, and encroachment management. The cutoff wall would consist of a bentonite (clay) and soil mixture created by excavation of a trench below the levee centerline; the trench would then be filled with the slurry. The levee would then be reconstructed over the wall. Contract D is approximately 11.4 miles in length (60,326 linear feet), and the construction footprint is typically approximately 240 feet wide.
Contact Information
Name
Kursten Sheridan
Agency Name
California Department of Fish and Wildlife
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Counties
Butte, Sutter
Cross Streets
Numerous
Zip
Numerous
Total Acres
1000
Parcel #
Numerous
State Highways
Hwy 99
Railways
UPRR
Airports
Butte County
Schools
Numerous
Waterways
Feather River
Other Location Info
Feather River west levee
Notice of Determination
Approving Agency
Department of Fish and Wildlife
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes