Downtown San Bernardino Passenger Rail Project

5 Documents in Project

Summary

SCH Number
2011051024
Lead Agency
San Bernardino Associated Governments
Document Title
Downtown San Bernardino Passenger Rail Project
Document Type
NOD - Notice of Determination
Received
Posted
5/9/2013
Present Land Use
General Plan: Industrial, Commercial General; Zoned: Commercial General (CG), CG-1, CG-2, Industrial Heavy, Industrial Light.
Document Description
The project will extend Metrolink regional passenger rail service approximately one mile east from its current terminus at the existing San Bernardino Metrolink Station/Santa Fe Depot (depot) to a new Metrolink commuter rail terminus proposed at the intersection of Rialto Avenue and E Street. The project will construct a second track, rail terminus and crew housing, parking lots, pedestrian pathways, an overpass at the depot, an Omnitrans bus facility, grade crossing improvements, railroad signalization, roadway closures, drainage improvements, utility accommodation and implementation of safety controls.

Contact Information

Name
Mitchell A. Alderman, P.E.
Agency Name
San Bernardino Associated Governments
Contact Types
Lead/Public Agency

Location

Cities
San Bernardino
Counties
San Bernardino
Cross Streets
Third Street to Rialto Avenue and E Street
Zip
92410
Total Acres
85
State Highways
I-215
Railways
BNSF/Metrolink
Schools
Richardson Middle
Waterways
Lytle Creek, Santa Ana River
Township
1S
Range
4W
Base
SBB&M

Notice of Determination

Approving Agency
California Transportation Commission
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print