Galt Wastewater Treatment Plant Solar Power Purchase Agreement Project
2 Documents in Project
Summary
SCH Number
2011042040
Lead Agency
City of Galt
Document Title
Galt Wastewater Treatment Plant Solar Power Purchase Agreement Project
Document Type
NOD - Notice of Determination
Received
Posted
6/9/2011
Present Land Use
The project site is on an existing holding pond of the City's wastewater treatment plant (WWTP). The existing General Plan land use designation and the zoning designation for the site are Public/Quasi-Public
Document Description
The proposed Project consists of the construction, operation and maintenance of up to a one megawatt solar photovoltaic (PV) array facility and related equipment on approximately 5.5 acres within a former holding pond at the Galt WWTP. The purpose of the project is to utilize solar electricity to supplement power for WWTP operations including the new ultraviolet disinfection and tertiary filtration facilities that were recently installed to comply with the national Pollutant Discharge Elimination System Permit (NPDES) for the WWTP. The project is part of a Solar Power Purchase Agreement whereby the solar provider, a private company, will lease the ground from the City of Galt and construct and operate the solar facility. In return, the City guarantees to purchase a minimum amount of electricity every year at a negotiated rate that is less than current and projected SMUD rates over a twenty year period.
Contact Information
Name
Sandra Kiriu
Agency Name
City of Galt, Planning Department
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Cities
Galt
Counties
Sacramento
Cross Streets
Twin Cities Road and SR-99
Zip
95632
Total Acres
5.45
Parcel #
148-0010-053
State Highways
SR-99, 104
Railways
UPRR
Schools
Lake Canyon ES, Richard A. McGee Correctional Training Center,
Waterways
Skunk Creek/Laguna Creek
Township
5N
Range
6E
Section
9
Base
MDB&M
Other Information
Cont. Schools: Kidz Come First Preschool
Notice of Determination
Approving Agency
City of Galt
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No