Downtown San Francisco Ferry Terminal Expansion Project

3 Documents in Project

Summary

SCH Number
2011032066
Lead Agency
San Francisco Bay Area Water Emergency Transit Authority
Document Title
Downtown San Francisco Ferry Terminal Expansion Project
Document Type
NOD - Notice of Determination
Received
Posted
10/6/2014
Present Land Use
Local Retail, Visitor & Specialty Retail, Office, R&D, Warehouse, Light Industry, and Ferry Excursion
Document Description
The project includes expansion and improvement of the Ferry Terminal at the Downtown San Francisco Ferry Building to accommodate construction of three new gates and overwater berthing facilities, in addition to supportive landside improvement, such as additional passenger waiting and queuing area, and circulation improvements. Construction is scheduled to commence as early as 2014 and be completed by 2020. The project supports existing and planned future water transit services operated by WETA, as well as WETA's emergency response operations.

Contact Information

Name
Mike Gougherty
Agency Name
San Francisco Bay Area Water Emergency Transit Authority
Contact Types
Lead/Public Agency

Location

Cities
San Francisco
Counties
San Francisco
Cross Streets
The Embarcadero and Market Street
Zip
94111
Total Acres
28
Parcel #
990002, 990200, 9900201, 9900274, 9900275, 9900278
State Highways
Hwy 101 and 280
Railways
Caltrain/Muni/BART/Amtrak
Schools
Youth Chance High School
Waterways
San Francisco Bay
Township
1/2S
Range
5
Section
34&3
Base
MDB&M

Notice of Determination

Approving Agency
WETA
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print