Hyatt Place Hotel Expansion and Old Davis Road Extension
4 Documents in Project
Summary
SCH Number
2011032051
Lead Agency
University of California
Document Title
Hyatt Place Hotel Expansion and Old Davis Road Extension
Document Type
NOD - Notice of Determination
Received
Posted
4/10/2012
Present Land Use
Academic and Administrative
Document Description
The project will extend Old Davis Road from its existing terminus east of the existing hotel to the southern terminus of A Street. The proposed extension of Old Davis Road has been previously identified as a component of the long-term UC Davis roadway plans and the road was partially extended by 800 feet in 2009 with the conference center and hotel construction projects. The proposed extension would construct approximately 1,100 feet of new roadway and would connect to the south side of Parking Lot 5 allowing through access on the connected roadway. Once connected, the road extension would provide an alternate route to the existing Old avis Road alignment. UC Davis eventually would convert the existing Old Davis Road along the south side of the UC Davis Arboretum to a bike and pedestrian path with emergency vehicle and service vehicle access.
Contact Information
Name
Sid England
Agency Name
University of California
Contact Types
Lead/Public Agency
Phone
Location
Cities
Davis
Counties
Yolo
Cross Streets
Old Davis Road and Mrak Hall Circle
Zip
95616
Total Acres
3
State Highways
SR 113, I-80
Railways
Union Pacific
Airports
University
Schools
Davis Joint Unified
Waterways
Putah Creek
Township
8N
Range
1E
Section
13
Base
MDB&M
Notice of Determination
Approving Agency
University of California
Approving Agency Role
Lead Agency
Determinations
(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes