Recycled Water Infrastructure Improvements

2 Documents in Project

Summary

SCH Number
2011031060
Lead Agency
Rowland Water District
Document Title
Recycled Water Infrastructure Improvements
Document Type
NOD - Notice of Determination
Received
Posted
7/22/2011
Present Land Use
The pipeline extension is located within existing road right-of-way and do not have a General plan or Zoning designation assigned. The pump stations are located in non-Urban 2 (N2) and zoned Agriculture (A-1). The reservoir is located in Urban (U1) designation and zoned Open Space with a Utility Easement.
Document Description
The project is recycled water infrastructure improvement in Rowland Heights and the City of Industry within the Rowland Water District service area. It includes extension of approximately 53,810 feet of pipelines, construction of two pump station sand construction of an above-ground reservoir.

Contact Information

Name
Ken Deck
Agency Name
Rowland Niguel Water District
Contact Types
Lead/Public Agency

Location

Cities
Industry
Counties
Los Angeles
Cross Streets
City of Industry - Rowland St. & Railroad St. Rowland Heights - Fullerton Rd. & Pathfinder Rd.
Zip
91744
State Highways
SR-60, SR-57
Railways
SPRR & UPRR
Waterways
San Juan Creek
Other Location Info
City/Nearest Community: Rowland Heights
Other Information
Continue Lat/Long: Rowland Heights - 33 58 5.81N/117 54 54.74 Continue Zip Code: 91748

Notice of Determination

Approving Agency
Rowland Water District Board of Directors
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print