Thunderhill Solar Power, LLC, Williamson Act 2010-006, Zone Change 2010-002, Cond. Use Permit 2010-002
2 Documents in Project
Download CSV
New Search
Print
Summary
- SCH Number
- 2011022051
- Lead Agency
- Glenn County
- Document Title
- Thunderhill Solar Power, LLC, Williamson Act 2010-006, Zone Change 2010-002, Cond. Use Permit 2010-002
- Document Type
- NOD - Notice of Determination
- Received
- Posted
- 4/1/2011
- Present Land Use
- "Agricultural Preserve Zone" / "Intensive Agriculture"
- Document Description
- The proposal includes a CUP application for the construction and operation of a 141.6 +/- acre Solar Photo-voltaic Power Generation Facility (including a new 60kV switch yard to be owned by PG&E), together with the Cancellation of an 111.7 +/- acre portion of Land Conservation Contract #1-14 and a Zone Change from Agricultural Preserve to Recreation and Planned Motor Sports.
- Contact Information
-
Andy Popper
Glenn County
Lead/Public Agency
Planning & Public Works Agency 777 North Colusa Street
Willows, CA 95988
Phone : (530) 934-6540
Location
- Coordinates
- 39°33'0"N 122°20'25"W
- Cities
- Willows
- Counties
- Glenn
- Cross Streets
- State Hwy 162
- Zip
- 95963
- Total Acres
- 141.6
- Parcel #
- 021-070-018 + 021-070-013
- State Highways
- Hwy 162
- Railways
- No
- Airports
- No
- Schools
- No
- Waterways
- No
- Township
- 20N
- Range
- 4W
- Section
- 32
- Base
- MDB&M
Notice of Determination
- Approving Agency
- Glenn County Board of Supervisors
- Approving Agency Role
- Lead Agency
- Approved On
- Final Environmental Document Available at
- N/A
Determinations
- (1) The project will have a significant impact on the environment
- No
- (2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
- No
- (2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
- Yes
- (2c) An other document type was prepared for this project pursuant to the provisions of CEQA
- No
- (3) Mitigated measures were made a condition of the approval of the project
- No
- (4) A mitigation reporting or monitoring plan was adopted for this project
- N/A
- (5) A Statement of Overriding Considerations was adopted for this project
- No
- (6) Findings were made pursuant to the provisions of CEQA
- Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.