Memorandum of Understanding for Water Service to the Shingle Springs Rancheria

5 Documents in Project

Summary

SCH Number
2011022045
Lead Agency
El Dorado Irrigation District
Document Title
Memorandum of Understanding for Water Service to the Shingle Springs Rancheria
Document Type
NOD - Notice of Determination
Received
Posted
2/12/2013
Present Land Use
Tribal Land
Document Description
Water service would be provided through a three-inch flow meter located on the Rancheria in an approximately five-foot seven-foot underground vault (flow meter vault) adjacent to Honpie Road. The meter would provide maximum continuous flow of 95 gpm and a maximum average daily delivery of 135,000 gpd. No physical changes would occur to EID's control, access, operation, maintenance, repair, or replacement capabilities. Water service on the Rancheria would be provided through a tribal utility district independent of EID. The new flow meter would be relocated approximately 2,000 feet to the southwest from the existing meter serving Rancheria. The flow meter would be connected to approximately 4,025 feet of new 12-inch water supply pipeline to be installed by the Tribe on the Rancheria along Honpie Road. The underground flow meter vault would be locked and EID would have sole access. Other appurtenances adjacent to the flow meter vault would include a backflow prevention assembly structure which would be approximately four feet tall. No new infrastructure would be constructed off the Rancheria in the EID service area and existing EID operations would remain unchanged.

Contact Information

Name
Dan Corcoran
Agency Name
El Dorado Irrigation District
Contact Types
Lead/Public Agency

Location

Counties
El Dorado
Cross Streets
Honpie Road
Zip
95667
Total Acres
<1
Parcel #
31910037
State Highways
Hwy 50
Schools
Buckeye ES, California Montessori Project
Waterways
Slate Creek
Township
10N
Range
10E
Section
29
Other Location Info
City/Nearest Community: Shingle Springs/Shingle Springs Rancheria

Notice of Determination

Approving Agency
El Dorado Irrigation District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes