Vallejo-Baylink Ferry Maintenance Facility

7 Documents in Project

Summary

SCH Number
2011022039
Lead Agency
Vallejo, City of (City of Vallejo)
Document Title
Vallejo-Baylink Ferry Maintenance Facility
Document Type
NOD - Notice of Determination
Received

Document Description
The Vallejo-Baylink Ferry Maintenance facility Project (project) would replace the existing maintenance facility at a location approximately half a mile downstream from the existing maintenance facility. The Project includes landside improvements as well as waterside improvements. Phase 1 of the landside improvements include relocation of the temporary administration offices at Building 477 to the project site, installation of fencing and security system, utility improvements, and installation of a fueling facility. The waterside improvements would cover approximately 16,000 square feet of water surface, of which approximately 11,000 square feet would be new facilities. The improvements include four new full-service berths and two mooring-only berths for the ferry vessels.

Contact Information
David Kleinschmidt
City of Vallejo, Planning Division
555 Santa Clara Street, 2nd Floor
Vallejo, CA 94590

(707) 648-4301

Location

Cities
Vallejo
Counties
Solano
Cross Streets
Nimitz Avenue / 7th Street / Waterfront Avenue
Zip
94592
Parcel #
0066-050-100
State Highways
Hwy 37, 80, 780
Railways
Abandoned Naval Railway
Schools
Mare Island Elementary
Waterways
Mare Island Strait
Township
3N
Range
4W
Section
14
Base
MDB&M
Other Location Info
City/Nearest Community: Mare Island

Notice of Determination

Approving Agency
City Council of the City of Vallejo
Approving Agency Role
Lead Agency
Approved On
Final EIR Available Location
N/A

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A Statement of Overriding Considerations was adopted for this project
No
(5) Findings were made pursuant to the provisions of CEQA
Yes
Download CSV New Search