Elk Grove-Florin Road Drainage System Improvements Project (Lake or Streambed Alteration Agreement No. 1600-2015-0085-R2).

7 Documents in Project

Summary

SCH Number
2011012035
Lead Agency
Elk Grove, City of (City of Elk Grove)
Document Title
Elk Grove-Florin Road Drainage System Improvements Project (Lake or Streambed Alteration Agreement No. 1600-2015-0085-R2).
Document Type
NOD - Notice of Determination
Received
Posted
8/5/2015
Present Land Use
Multiple, including: commercial, industrial, residential, recreational, open space, small-scale agricultural, mixed use, and public...

Document Description
CDFW has executed Lake and Streambed Alteration Agreement No. 1600-2015-0085-R2, pursuant to section 1602 of the Fish and Game Code to the project Applicant, City of Elk Grove. The proposed project will remove the existing storm drain outfall and concrete bag headwall and replace it with a new storm drain outfall and concrete bag slope protection. The existing box culvert will be left in place. The proposed project will remove 15 cubic yards (CY) of earth from Whitehouse Creek and will install 15 CY of rock slope protection (RSP) and RSP fabric. At the outfall the project will remove 3.5 CY of earth and will install 4.3 CY of concrete. The construction of the project will result in 0.004 acres of permanent impacts and 0.03 acres of temporary impacts to Department jurisdictional areas.

Contact Information
Juan Lopez Torres
CDFW North Central Region
1701 Nimbus Road, Suite A
Rancho Cordova, CA 95670

Phone : (916) 358-2951

Location

Coordinates
38°25'5"N 121°23'41"W
Cities
Elk Grove
Counties
Sacramento
Cross Streets
Citywide Drainage Improvements
Zip
95758
Total Acres
50
Parcel #
Multiple
State Highways
I-5, SR-99
Railways
No
Airports
No
Schools
No
Waterways
Multiple, including Laguna Creek, Elk Grove Creek

Notice of Determination

Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On
Final EIR Available Location
CDFW North Central Region, 1701 Nimbus Road, Suite A, Rancho Cordova, CA 95670

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A Statement of Overriding Considerations was adopted for this project
No
(5) Findings were made pursuant to the provisions of CEQA
Yes