Eastside Test Wells

2 Documents in Project

Summary

SCH Number
2011011043
Lead Agency
City of Big Bear Lake
Document Title
Eastside Test Wells
Document Type
NOD - Notice of Determination
Received
Posted
3/18/2011
Document Description
The objective of the proposal test wells is to locate a municipal water well in the Erwin Subunit to meet future demand of existing and future connection. The proposed test wells would provide the DWP with information to assess the quantity and quality of groundwater at each location. The amount of drawdown and potential effect on surrounding wells may also be determined. Is the test results indicated that any are suitable for production well, the DWP will perform a second-tier evaluation of this action based on the procedures outlined in the State CEQA Guidelines, Section 15162 and 15166. The DWP selected proposed test well locations based on a hydrogeologic technical study prepared by Thomas Harder & Company, Groundwater Consulting titled "Analysis of Potential Well Sites." The proposed project consists of drilling up to five new groundwater wells. Surrounding land uses at all location is low to moderate density residences, except those in the Camp Oaked (Upper Arrastre Creek Drainage), which consists of very low density residential development and open space.

Contact Information

Name
Bill La Haye
Agency Name
City of Big Bear Lake Dept. of Water and Power
Contact Types
Lead/Public Agency

Location

Cities
Big Bear Lake
Counties
San Bernardino
Cross Streets
SH 38 and Baldwin Lane
Zip
92314
Total Acres
~ 5
State Highways
Hwy 38
Waterways
Baldwin Lake
Township
2N
Range
2E
Section
27
Base
SBB&M

Notice of Determination

Approving Agency
City of Big Bear Lake DWP
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.