Addnedum to Long-Term Water Transfers EIS/EIR

10 Documents in Project

Summary

SCH Number
2011011010
Lead Agency
San Luis and Delta Mendota Water Authority
Document Title
Addnedum to Long-Term Water Transfers EIS/EIR
Document Type
NOD - Notice of Determination
Received

Document Description
The Long-Term Water Transfers EIS/EIR was certified in 2015. Additional agencies not previously identified in the EIS/EIR have since indicated that they may be interested in water transfers, and three agencies that were already identified in the EIS/EIR indicated an interest in increasing their amount of potential water transfers. These water transfers refine the range of potential transfers specifically acknowledged in the Long-Term Water Transfers EIS/EIR. While individual agencies may be able to transfer additional water, the overall water transfers in total for all agencies would not exceed the 511,094 acre-feet analyzed in the EIS/EIS. SLDMWA prepared an Addendum to evaluate the potential differences between the impacts analyzed in the EIS/EIR and those associated with project refinements. SLDMWA determined that the refinements tot eh range of potential water transfers would not result in new or substantially more severe environmental effects and do not require further environmental review.

Contact Information
Frances Mizuno
San Luis & Delta-Mendota Water Authority
P.O. Box 2157 842 6th Street
Los Ganos, CA 93635

209-832-6200

Location

Coordinates
37°03'40.1"N 120°50'51.5"W
Counties
Sacramento Placer Nevada Merced Glenn Colusa Butte
Cross Streets
n/a
Parcel #
n/a

Notice of Determination

Approving Agency
San Luis & Delta-Mendota Water Authority
Approving Agency Role
Lead Agency
Approved On
Final EIR Available Location
842 6th Streeet, Los Banos, CA 93635

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A Statement of Overriding Considerations was adopted for this project
No
(5) Findings were made pursuant to the provisions of CEQA
Yes
Download CSV New Search