Code Amendment (Planning Case Nos. ZON2010-00183)

2 Documents in Project

Summary

SCH Number
2011011001
Lead Agency
City of Rancho Palos Verdes
Document Title
Code Amendment (Planning Case Nos. ZON2010-00183)
Document Type
NOD - Notice of Determination
Received
Posted
11/13/2013
Present Land Use
Varies, since project is Citywide
Document Description
The Project involves constructing the Lockhart Substation and associated facilities to interconnect the 250 megawatt Abengoa Mojave Solar Project to Southern California Edison's existing Coolwater-Kramer No. 1 220 kilovolt transmission line. In order to support the interconnection, a telecommunications Special Protection System will be required to provide transmission line protection, monitoring, and remote operation capabilities of the electrical equipment at Lockhart Substation. This proposed project involves construction and operation of a new lateral pipeline , a new tap and pig launcher will be constructed within and immediately adjacent to Kern River's right-of-way (ROW), and a new meter station and pig receiver will be constructed within the Molycorp site. The Project will result in permanent impacts to 23.22 acres of Mohave ground squirrel and desert tortoise habitat resulting in incidental take of individuals of these species, both of which have been designated as threatened under the California Endangered Species Act (CESA). The incidental take permit issued by DFW, authorizes incidental take of species listed under CESA that may occur as a result of Project implementation.

Contact Information

Name
Kimberly Nicol
Agency Name
Department of Fish and Wildlife
Contact Types
Lead/Public Agency

Location

Cities
Rancho Palos Verdes
Counties
Los Angeles
Regions
Citywide
Cross Streets
Citywide
Zip
90275
State Highways
Hwy 1 and 213
Railways
no
Waterways
Pacific Ocean to the south and west

Notice of Determination

Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.