Rancho Tajiguas 2017 Storm Damage Repair- T6/T7 (Streambed Alteration Agreement No. 1600-2017-0173-R5)
37 Documents in Project
Download CSV
New Search
Print
Summary
- SCH Number
- 2010122088
- Lead Agency
- Fish & Game #2
- Document Title
- Rancho Tajiguas 2017 Storm Damage Repair- T6/T7 (Streambed Alteration Agreement No. 1600-2017-0173-R5)
- Document Type
- NOD - Notice of Determination
- Received
- Posted
- 12/13/2017
- Document Description
- CDFW has executed Streambed Alteration Agreement No. 1600-2017-0173-R5, pursuant to section 1602 of the Fish and Game Code to the project Applicant, MAZ Properties, Inc. c/o Alicia Harrison. Project falls under the 2011 Fisheries Restoration Grant Program. Permittee previously completed the removal and subsequent stream restoration of five instream barriers to fish passage along Tajiguas Creek. A series of storm events in January and February of 2017 caused damage at two areas of restoration. Permittee proposes to make the following repairs to the damaged restoration areas: The damaged restoration areas along the streambanks at both sites will undergo minor excavation to allow for placement of rock slope protection (RSP), placement of backfill behind RSP, planting of live willow stakes, and placement of geotextile cloth. All remaining voids within the RSP will be filled with salvaged material less than three inches in diameter. Repairs include revegetation of streambanks with plants locally native to the area. In the event that water is present, a dewatering plan will be implemented.
- Contact Information
-
Sarah Rains
California Department of Fish and Wildlife
3883 Ruffin Road
San Diego, CA 92123
Phone : (805) 498-2385
Location
- Cities
- Goleta
- Counties
- Del Norte Humboldt Madera Mendocino Napa
- Cross Streets
- Various coastal counties
Notice of Determination
- Approving Agency
- California Department of Fish and Wildlife
- Approving Agency Role
- Lead Agency
- Approved On
- Final Environmental Document Available at
- 3883 Ruffin Road, San Diego, CA 92123
Determinations
- (1) The project will have a significant impact on the environment
- No
- (2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
- No
- (2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
- Yes
- (2c) An other document type was prepared for this project pursuant to the provisions of CEQA
- No
- (3) Mitigated measures were made a condition of the approval of the project
- Yes
- (4) A mitigation reporting or monitoring plan was adopted for this project
- N/A
- (5) A Statement of Overriding Considerations was adopted for this project
- No
- (6) Findings were made pursuant to the provisions of CEQA
- No
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.