Willits Education Center Negative Declaration/Initial Study

2 Documents in Project

Summary

SCH Number
2010122040
Lead Agency
Mendocino-Lake Community College District
Document Title
Willits Education Center Negative Declaration/Initial Study
Document Type
NOD - Notice of Determination
Received
Posted
1/14/2011
Present Land Use
Currently vacant site formerly used for furniture manufacturing/Heavy Manufacturing (MH)/ Heavy Manufacturing (MH)
Document Description
Development of a new permanent educational center to serve the community of Willits and the northern part of Mendocino County. Temporary facilities, at several locations in the city that are currently leased, would be consolidated onto the proposed 4.1 acre project site. The project would be built in three phases with an eventual total of 30,800 square feet of structures, 159 parking spaces with access from North Lenore Avenue, a central plaza, and landscaping. Completion of the project has been scheduled for Fall 2013. At full capacity, total enrollment would be ~ 1,200 full and part-time students, with 600 to 700 individual full-time equivalent (one student for ~ 12 hours per week) students attending classes at both the new center and on-line via the internet.

Contact Information

Name
Mike Adams
Agency Name
Mendocino-Lake Community College District
Contact Types
Lead/Public Agency

Location

Cities
Willits
Counties
Mendocino
Cross Streets
Comercial Street/North Lenore Avenue
Zip
95490
Total Acres
4.1
Parcel #
005-130-21
State Highways
20; US Hwy 101
Railways
Skunk Train; NW Pacific
Airports
no
Schools
Willits HS, Willits Sec.
Waterways
Broaddus Creek; Mill Creek, Baechtel Creek et. al.
Township
18N
Range
13W
Section
18
Base
MDB&M

Notice of Determination

Approving Agency
Mendocino-Lake CCD Board of Trustees
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.

Download CSV New Search Print