Renewable Solar and Wind Energy General Plan Amendment (General Plan Amendment No. 2010-03/Inyo County)
2 Documents in Project
Summary
SCH Number
2010121050
Lead Agency
Inyo County
Document Title
Renewable Solar and Wind Energy General Plan Amendment (General Plan Amendment No. 2010-03/Inyo County)
Document Type
NOD - Notice of Determination
Received
Posted
4/26/2011
Present Land Use
All
Document Description
NOTE: Extended Review per lead
An update to the Inyo County General Plan is proposed to address renewable solar and wind energy development. As part of the update, a General Plan Land Use Designation Overlay is proposed in which renewable energy projects, specifically solar and wind, may be developed, based on site specific studies pursuant to the County's Renewable Energy Ordinance and other applicable State, federal, and local laws. Other updates proposed include the following: identifying appropriate means to develop renewable wind and solar energy resources, provided that social economic, and environmental impacts are minimized; offsetting costs to the County and lost economic development potential, and mitigation of economic effects; working to protect military readiness, and considering conversions of lands utilized for agriculture, mining, and recreation.
Contact Information
Name
Josh Hart
Agency Name
Inyo County Planning Department
Contact Types
Lead/Public Agency
Phone
Location
Counties
Inyo
Regions
Countywide
Cross Streets
County-wide
Notice of Determination
Approving Agency
Inyo County Board of Supervisors
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.