Maple Street Replacement Facility Project (MSRF)

2 Documents in Project

Summary

SCH Number
2010112028
Lead Agency
San Mateo County
Document Title
Maple Street Replacement Facility Project (MSRF)
Document Type
NOD - Notice of Determination
Received
Posted
12/27/2010
Present Land Use
As a County Government Facility, the MSRF would be exempt from zoning, but current zoning is Industrial - Restricted
Document Description
Proposed MSRF project includes a 768-bed correctional facility and surface parking for 164 vehicles. The MSRF would replace three existing correctional facilities at 1580 and 1590 Maple Street in Redwood City, CA and alleviate overcrowding in a fourth facility in downtown Redwood City, CA. Project construction would require the deconstruction or demolition of existing light industrial buildings on the project site, site preparation and building construction, and utility improvements. In addition, the Sheriff's Office would make minor modification to the Maguire Correctional Facility (MCF) to accommodate changes to existing visitation and support service operations that would occur with operation of the MSRF.

Contact Information

Name
Lieutenant Deborah Bazan
Agency Name
San Mateo County
Contact Types
Lead/Public Agency

Location

Cities
Redwood City
Counties
San Mateo
Cross Streets
Maple Street and Blomquist Street
Zip
94063
Total Acres
4.69
Parcel #
052-392-190, 200, 210, 240, 260, 270
State Highways
US 101
Railways
Yes
Airports
San Carlos
Schools
Orion, Hoover
Waterways
Redwood Creek, S.F. Bay

Notice of Determination

Approving Agency
County of San Mateo
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.