Pacific Gas and Electric Company (PG&E) Crazy Horse Canyon Switching Station and Hollister 115kV Power Line Reconductoring Project (California Endangered Specie

8 Documents in Project

Summary

SCH Number
2010111065
Lead Agency
California Public Utilities Commission (CPUC)
Document Title
Pacific Gas and Electric Company (PG&E) Crazy Horse Canyon Switching Station and Hollister 115kV Power Line Reconductoring Project (California Endangered Specie
Document Type
NOD - Notice of Determination
Received
Posted
7/1/2014
Present Land Use
Grazing, agricultural, rangeland uses.
Document Description
The Project is comprised of two actions: (1) the reconductoring of an existing power line system by rebuilding it as a double circuit line through the replacement of poles and towers and upgrading the substations and (2) constructing a new switching station to connect several transmission lines into a common bus. The two actions have overlapping work and impact areas totaling approximately 2.5 acres. Minor Amendment No.2 extends to 48 months the deadline by which completion of Habitat Management (HM) land protection must occur. The Project will result in impacts to 79.02 acres of CA tiger salamander (Ambystoma californiense) and San Joaquin kit fox (Vulpes macrotis mutica) habitat including temporary impacts to 72.1 acres; the Project will permanently remove 6.32 acres of CA tiger salamander and San Joaquin kit fox habitat. The project is expected to result in incidental take of CA tiger salamander and San Joaquin kit fox, which are designated as a threatened species under the CA Endangered Species Act. The ITP, Major Amendment No.1, and Minor Amendment No.2 (collectively, the ITP, as amended) authorizes incidental take of species listed under CESA that may occur as a result of Project Implementation. CDFW issued the ITP, as amended, as a responsible agency under the California Environmental Quality Act (CEQA) relying on the Mitigated Negative Declarations prepared and certified for the Project by the lead agency, the California Public Utilities Commission (CPUC).

Contact Information

Name
Sarah Bahm
Agency Name
CDFW Central Region
Contact Types
Lead/Public Agency

Location

Cities
Hollister, San Juan Bautista
Counties
Monterey, San Benito
Cross Streets
Multiple (Substation at Bolsa Road, San Felipe Road)
Zip
95023
Parcel #
Multiple
State Highways
Hwy 156, 25, 129, 101
Railways
UPRR
Airports
Hollister Municipal
Schools
Multiple
Waterways
San Benito River
Other Location Info
Prunedale

Notice of Determination

Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print