PG&E Crazy Horse Canyon Switching Station and Hollister 115kV Power Line Reconductoring Project (CA Endangered Species Act incidental Take Permit No. 2081-2011-

8 Documents in Project

Summary

SCH Number
2010111065
Lead Agency
Public Utilities Commission (California Public Utilities Commission)
Document Title
PG&E Crazy Horse Canyon Switching Station and Hollister 115kV Power Line Reconductoring Project (CA Endangered Species Act incidental Take Permit No. 2081-2011-
Document Type
NOD - Notice of Determination
Received

Document Description
The project is comprised of two actions: (1) the reconductoring of an existing power line system by rebuilding it as a double circuit line through the replacement of poles and towers and upgrading the substations and (2) constructing a new switching station to connect together several different transmission lines into a common bus. The project will result in impacts to 79.02 acres of CA tiger salamander and San Joaquin kit fox habitat including temporary impacts to 72.1 acres; the project will permanently remove 6.32 acres of CA tiger salamander and San Joaquin kit fox habitat. The project is expected to result in incidental take of CA tiger salamander and San Joaquin kit fox, which are designated as a threatened species under the CA Endangered Species Act. The ITP referenced above as issued by DFG authorizes incidental take of species listed under CESA that may occur as a result of project implementation.

Contact Information
Brandon Sanderson
DFG
1234 East Shaw Avenue
Fresno, CA 93710

805 594-6151

Location

Coordinates
36°52'18"N 121°24'28"W
Cities
San Juan Bautista Hollister
Counties
San Benito Monterey
Cross Streets
Multiple (Substation at Bolsa Road, San Felipe Road)
Zip
95023
Parcel #
Multiple
State Highways
Hwy 156, 25, 129, 101
Railways
UPRR
Airports
Hollister Municipal
Schools
Multiple
Waterways
San Benito River

Notice of Determination

Approving Agency
DFG
Approving Agency Role
Responsible Agency
Approved On
Final EIR Available Location
N/A

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A Statement of Overriding Considerations was adopted for this project
No
(5) Findings were made pursuant to the provisions of CEQA