PG&E Hollister 115 kV Power Line Reconductoring Project
8 Documents in Project
Download CSV
New Search
Print
Summary
- SCH Number
- 2010111065
- Lead Agency
- Public Utilities Commission, California (California Public Utilities Commission)
- Document Title
- PG&E Hollister 115 kV Power Line Reconductoring Project
- Document Type
- NOD - Notice of Determination
- Received
- Posted
- 2/14/2011
- Present Land Use
- Grazing, agricultural, rangeland uses.
- Document Description
- Replacement of seven miles of single circuit power line towers with new single circuit power line towers; replacement of nine miles of single circuit power line poles with new double circuit poles; and upgrades to Hollister Substation.
- Contact Information
-
Mary Jo Borak
California Public Utilities Commission
505 Van Ness Avenue
San Francisco, CA 94102-3298
Phone : (415) 703-1333
Location
- Coordinates
- 36°52'18"N 121°24'28"W
- Cities
- Hollister San Juan Bautista
- Counties
- Monterey San Benito
- Cross Streets
- Multiple (Substation at Bolsa Road, San Felipe Road)
- Zip
- 95023
- Parcel #
- Multiple
- State Highways
- Hwy 156, 25, 129, 101
- Railways
- UPRR
- Airports
- Hollister Municipal
- Schools
- Multiple
- Waterways
- San Benito River
Notice of Determination
- Approving Agency
- California Public Utilities Commission
- Approving Agency Role
- Lead Agency
- Approved On
- Final Environmental Document Available at
- http://www.cpuc.ca.gov/Environment/info/esa/hollister/hollister.html
Determinations
- (1) The project will have a significant impact on the environment
- No
- (2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
- No
- (2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
- Yes
- (2c) An other document type was prepared for this project pursuant to the provisions of CEQA
- No
- (3) Mitigated measures were made a condition of the approval of the project
- Yes
- (4) A mitigation reporting or monitoring plan was adopted for this project
- N/A
- (5) A Statement of Overriding Considerations was adopted for this project
- No
- (6) Findings were made pursuant to the provisions of CEQA
- Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.