Sabre Springs/Penasquitos I-15 Transit Center Parking Structure

2 Documents in Project

Summary

SCH Number
2010111018
Lead Agency
San Diego Association of Governments
Document Title
Sabre Springs/Penasquitos I-15 Transit Center Parking Structure
Document Type
NOD - Notice of Determination
Received
Posted
2/25/2011
Present Land Use
Zoning: Community Commercial (CC-2-3) General Plan Designation: Speciality Commercial
Document Description
NOTE: Extended review The project consists of the construction of a parking structure and associated improvement within the Sabre Springs/Penasquitos Transit Center. The parking structure would be limited to four stories above existing grade and would be located in the southern portion of the transit center, adjacent to Carmel Mountain Express Drive and Sabre Springs Parkway. The new transit center would accommodate a minimum of 630 parking spaces in a combination of structure and surface parking. Circulation within the transit center would be revised to accommodate the new structure. Security lighting would be installed within the parking structure and maintained or replaced where appropriate to provide adequate lighting during morning and nighttime operating hours. The transit center is planned to be closed to accommodate staging and construction.

Contact Information

Name
Rob Rundle
Agency Name
San Diego Association of Governments
Contact Types
Lead/Public Agency

Location

Cities
San Diego
Counties
San Diego
Cross Streets
Ted Williams Parkway (SR 56) and Sabre Springs Parkway
Zip
92128
Total Acres
4
Parcel #
316-420-0400, -0500, -0200, -0300
State Highways
Hwy 56
Schools
Morning Creek
Other Location Info
City/Nearest Community: Sabre Springs

Notice of Determination

Approving Agency
SANDAG Transportation Committee
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print