Drumright Subdivision

Summary

SCH Number
2010109005
Lead Agency
Planning and Research, Office of (Office of Planning and Research)
Document Title
Drumright Subdivision
Document Type
NOD - Notice of Determination
Received

Document Description
The project is a multi-use subdivision, which will consist of Drumright Wine Warehouse and Tasting Facility, Healdsburg Animal Shelter, and Clendenen Vineyard Management Drumright Wine Warehouse and Tasting Facility will be constructed on approximately 8.88 acres of the original parcel. The facility will consist of an approximately 64,000sf wine warehouse building, including case storage, tank processing area, tasting room and office space. Healdsburg Animal Shelter will construct an approximately 12,691sf building, containing kennels, a domestic animal clinic, training room, observation area, waiting room, and administrative offices on approximately 2.82 acres of the project site. Clendenen Vineyard Management Company will consist of two structures, totaling approximately 13,200sf, and an outdoor storage yard, and will be separated from the north property line by a sound berm. The project also incorporates a riparian restoration and mitigation area of approximately 2.89 acres adjacent to the top of the bank of Dry Creek, on the western edge of the project. The California Department of Fish and Game is executing a Lake and Streambed Alteration Agreement Number 1600-2009-0268-R3 pursuant to Section 1602 of the Fish and Game Code to the project Applicant, Jim and Linda Drumright.

Contact Information
Adam McKannay
California Department of Fish and Game
P.O. Box 47
Yountville, CA 94559

707-944-5534

Location

Cities
Healdsburg
Counties
Sonoma

Notice of Determination

Approving Agency
California Department of Fish and Game
Approving Agency Role
Responsible Agency
Approved On
Final EIR Available Location
2550 Ventura Ave Santa Rosa, CA

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(3) Mitigated measures were made a condition of the approval of the project
N/A
(4) A Statement of Overriding Considerations was adopted for this project
N/A
(5) Findings were made pursuant to the provisions of CEQA
N/A
Download CSV New Search