Fremont Avenue Bridge Replacement Project

2 Documents in Project

Summary

SCH Number
2010102052
Lead Agency
Los Altos, City of (City of Los Altos)
Document Title
Fremont Avenue Bridge Replacement Project
Document Type
NOD - Notice of Determination
Received
Posted
1/31/2011
Present Land Use
"Collector" roadway in the General Plan. Permanente Creek corridor is designated as "Open Space" in the General Plan.

Document Description
The project will replace the Fremont Avenue Bridge over Permanente Creek which is approaching the end of its useful life. The new bridge design includes demolition of the existing bridge structure and replacement with a new bridge widened to accommodate two 12 foot vehicle lanes with 5 foot wide bicycle lanes in both directions. The "crash rated" concrete barriers will have an aesthetic treatment to better match the existing adjacent wooden foot bridge located on the north side that will remain. Outside of the concrete barriers, an attached pedestrian sidewalk with creek overlook feature is to be constructed on the south side of the bridge.

Contact Information
Adam C Porter
City of Los Altos
1 N. San Antonio Road
Los Altos, CA 94022

Phone : (650) 947-2623
Fax : (650) 947-2733

Location

Coordinates
37°21'08"N 122°05'08"W
Cities
Los Altos
Counties
Santa Clara
Cross Streets
Fremont Avenue and Miramonte Avenue
Zip
94024
Total Acres
0.03
State Highways
SR 85; I-280
Schools
Blach, Mountclaire
Waterways
Permanente Creek
Township
7S
Range
2W
Section
4

Notice of Determination

Approving Agency
City of Los Altos
Approving Agency Role
Lead Agency
Approved On
Final Environmental Document Available at
Engineering Division Los Altos City Hall One North San Antonio Road Los Altos, CA 94022

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.