Atascadero - San Luis Obispo 70 kV Power Line Reconductoring Project, Streambed Alteration Agreement No. 2010-0055-R4, and 2010-0057-R4
3 Documents in Project
Summary
SCH Number
2010101063
Lead Agency
California Public Utilities Commission
(CPUC)
Document Title
Atascadero - San Luis Obispo 70 kV Power Line Reconductoring Project, Streambed Alteration Agreement No. 2010-0055-R4, and 2010-0057-R4
Document Type
NOD - Notice of Determination
Received
Posted
7/27/2011
Document Description
The California Department of Fish and Game is executing a Streambed Alteration Agreement pursuant to Section 1602 of the Fish and Game Code to the Project applicant, Pacific Gas and Electric Company (PG&E), for the Atascadero-San Luis Obispo 70 kV Power Line Reconductoring Project. The applicant proposes to install temporary or permanent culverts, bridges, and or steel plates so as to create vehicle and equipment crossings over the channel at 10 locations. Temporary installations will be removed and locations restored upon Project completion.
Contact Information
Name
Amy Krisch
Agency Name
DFG, Central Region
Contact Types
Lead/Public Agency
Phone
Location
Cities
Atascadero, San Luis Obispo
Counties
San Luis Obispo
Cross Streets
along US 101, from Santa Rosa Rd & SR 41,Atascadero to Orcutt Rd & Johnson Ave
Zip
93422/01
Total Acres
~977
State Highways
Hwy 101, 58, 41
Railways
Amtrak
Airports
San Luis Obispo County Regional
Schools
9 public & private
Waterways
several
Township
Sev
Range
Sev
Section
Sev
Notice of Determination
Approving Agency
DFG
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.