Chino Desalter Phase 3 Expansion Project

11 Documents in Project

Summary

SCH Number
2010101061
Lead Agency
Chino Basin Municipal Water District
Document Title
Chino Desalter Phase 3 Expansion Project
Document Type
NOD - Notice of Determination
Received
Posted
1/13/2011
Document Description
The Chino Desalter Phase 3 Expansion Project consists of an expansion of groundwater extraction and treatment in the southern portion of the Chino Basin from an existing 27,000 acre-feet annually to ~ 40,000 acre-feet annually. The project consists of installing and operating the following equipment and components; up to six new wells; new pipelines to deliver the raw water to the Chino I and II Desalters; new treatment facilities at the Chino II Desalter to treat the additional raw water; a possible concrete reduction facility at the Chico II Desalter; up to four pump stations to transfer product water to potable water suppliers; an new pipelines to deliver the product (treated) water to water suppliers. Once installed, this expanded Desalter system will require electricity to operate wells, pump stations and expanded desalter facilities, and a small quantity of reject water may be disposed of through the Santa Ana Regional Interceptor line for treatment in Orange County.

Contact Information

Name
Timothy Mim Mack
Agency Name
Chino Basin Desalter Authority
Contact Types
Lead/Public Agency

Location

Cities
Ontario
Counties
San Bernardino
Cross Streets
S. portion of Chino Basin, generally S. of SH 60 & N. of Prado Basin
State Highways
Hwy 60
Railways
UPRR
Airports
Chino Airport
Waterways
Santa Ana River

Notice of Determination

Approving Agency
Chino Basin Desalter Authority
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print