Use Permit No. 858-02(A)
2 Documents in Project
Download CSV
New Search
Print
Summary
- SCH Number
- 2010091071
- Lead Agency
- San Benito County
- Document Title
- Use Permit No. 858-02(A)
- Document Type
- NOD - Notice of Determination
- Received
- Posted
- 12/2/2010
- Present Land Use
- AR-Agricultural Rangeland
- Document Description
- The California Department of Fish and Game is executing a Lake and Streambed Alteration Agreement pursuant to Section 1602 of the Fish and Game Code for the Vegetation and Sediment Maintenance Program at Los Banos Detention Dam Project. The objectives of the Project are to remove vegetation, including non-native and native trees that may prohibit flow, from the outflow channel and the basin and to restore the area below the spillway structure (knows as the "horseshoe" area due to its shape) close to original design and specification. This vegetation removal will allow water to flow downstream away from the dam and the toe drain.
- Contact Information
-
Annette Tenneboe
California Department of Fish and Game Central Region
Lead/Public Agency
1234 East Shaw Avenue
Fresno, CA 93710
Phone : (559) 243-4014 x 231
Location
- Coordinates
- 36°41'7.71"N 121°21'28.9"W
- Counties
- San Benito
- Cross Streets
- Limekiln and Cienega
- Zip
- 95023
- Total Acres
- 678.77
- Parcel #
- 026-110-002 & 026-040-014
- Waterways
- Thompson Creek
- Other Location Info
- City/Nearest Community: Paicines
Notice of Determination
- Approving Agency
- California Department of Fish and Game
- Approving Agency Role
- Responsible Agency
- Approved On
- Final Environmental Document Available at
- Department of Water Resources SCRO 3374 East Shields Avenue Fresno, CA 93726
Determinations
- (1) The project will have a significant impact on the environment
- Yes
- (2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
- No
- (2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
- Yes
- (2c) An other document type was prepared for this project pursuant to the provisions of CEQA
- No
- (3) Mitigated measures were made a condition of the approval of the project
- Yes
- (4) A mitigation reporting or monitoring plan was adopted for this project
- N/A
- (5) A Statement of Overriding Considerations was adopted for this project
- No
- (6) Findings were made pursuant to the provisions of CEQA
- Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.